 Mechanical maintenance in the 4 groups from the thermal power plant of As Pontes

Project made by Daorje

 Work done:

Mechanical maintenance of the following systems in the 4 groups (4x350MW/ud) of the C.T. As Pontes:

  • System of fuel preparation.
  • System of coal and ashes.
  • System of the auxiliary turbine.
  • System of the boiler, including the repairing of Pinchazos.

Industrial cleaning of the plant.

Mechanical maintenance of the equipment of the mine, including the vulcanized.

 Work done:

Mechanical maintenance of the following systems in the 4 groups (4x350MW/ud) of the C.T. As Pontes:

  • System of fuel preparation.
  • System of coal and ashes.
  • System of the auxiliary turbine.
  • System of the boiler, including the repairing of Pinchazos.

Industrial cleaning of the plant.

Mechanical maintenance of the equipment of the mine, including the vulcanized.

Project made by Daorje

Client

ENDESA

Sector

Energetic

Location

As Pontes, España

Period

18 años

Client

ENDESA

Location

As Pontes, España

Sector

Energetic

Period

18 años

 Otther related projects